Hi Nigel
I think the problem has been that the activity plan has lacked any substance for a while ... I'd agree with this. It is both too detailed and not detailed enough.
It would be good to see costs all be they in retrospect in at least part for this year's activity plan.
I would also quite like an answer to the question I raised at the GM in respect to the costs for the RPKI project.
You kindly admitted that you had exact costs for the project and then completely failed to provide them despite that being the point of my question. I didn't provide them at the meeting largely because I don't have them in my head. We can certainly provide them to you. Jochem usually, when doing his budget presentation, indicates roughly how the various budget
On 07/11/2011 11:39, Jon Morby wrote: lines are made up and there is usually a full and detailed budget in the back of the Annual report. We'll make sure we get them to you, as I indicated we would.
I would be grateful for a completion of the answer; all be it too late to affect the outcome of the vote at the GM. However I think it would be useful to see how much of the overall budget is assigned to this project, and all other activities currently underway. The fact no costs / budgets have been included in the activity plan over the last few years is an innocent oversight I'm sure, but it would be useful to correct this now as you have already stated, and it would be helpful to see the costs for this year both actual and budgeted ...
However, as I indicated, a very full budget is included in the Annual report, a copy of which is sent to every member (and which is available online). It *doesn't* break down to individual activities, but we have this information and will get it to you. Annual reports all the way back to 1998 are available at http://www.ripe.net/internet-coordination/press-centre/publications/annual-r... Best regards Nigel